Question: A project is considered completed when activities A-F have all been completed. The duration and predecessors of each activity are given in Table 43. Determine

A project is considered completed when activities A-F have all been completed. The duration and predecessors of each activity are given in Table 43. Determine a critical path in the network. What is t 