Question: A project is nearing completion when the project team learns of new regulations for the region where the product is to be installed. The project
A project is nearing completion when the project team learns of new regulations for the region where the product is to be installed. The project manager determines that a new feature will have to be added to ensure compliance, which will impact the resources, schedule, and budge. What is needed to communicate and apply the activities required to comply with these new Regulations?
A. Risk breakdown structure (RBS)
B. Change control
C. Issue log
D. Process analysis