Question: A project is one week long ( Mon - rri ) and has tour tasks, A , B , C and D . The tasks

A project is one week long (Mon-rri) and has tour tasks, A,B,C and D. The tasks were initially estimated to have daily costs of R50, R100, R200 and R100 respectivel/ However, by end of Tuesday, Task A is 100% complete, task B is 90% complete and C is 30% complete. (See Gantt chart below).
\table[[Day,Mon,Tue,Wed,Thur,Fri,\table[[Budget],[For],[whole],[Task/R]],\table[[%],[Complete],[by],[Tuesday]],\table[[Actualoo],[Cost by],[Tuesday]]],[Task,,,,,,50,100,60],[B,,,,,,100,80,110],[C,,,,,,100,20,30],[D,,,,,,200,0,0],[,,,,,,100,0,]]
Determine the BCWS by end of business, Tuesday:
A.150
B.450
C.250
D.350
 A project is one week long (Mon-rri) and has tour tasks,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!