Question: A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length
A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology?
| Activity | Predecessor | Length | Activity | Predecessor | Length |
| M | -- | 8 | R | -- | 12 |
| N | -- | 8 | S | P | 14 |
| P | M | 12 | T | R, Q | 7 |
| Q | N | 10 | V | S, T | 11 |
Group of answer choices
13.5
22.5
11.25
9.0
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
