Question: A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length

A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology?

Activity Predecessor Length Activity Predecessor Length
M -- 8 R -- 12
N -- 8 S P 14
P M 12 T R, Q 7
Q N 10 V S, T 11

Group of answer choices

13.5

22.5

11.25

9.0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!