Question: Answer is 16. How do you get to the answer? What are the steps? 71) A project is represented by the activity durations (estimated at
Answer is 16. How do you get to the answer? What are the steps?

71) A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology? ActivityPedssor Length ActivityPredecessor Length 20 20 10 13 16 1D, 1 71) A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology? ActivityPedssor Length ActivityPredecessor Length 20 20 10 13 16 1D, 1