Question: Answer is 48. Can someone explain the steps to get there? 72) A project is represented by the activity durations (estimated at 90% likelihood of
Answer is 48. Can someone explain the steps to get there?

72) A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the overall duration of this project if it is managed using critical chain methodology? ActivityPredecessor LengthAcivityPredecessor Length 16 20 20 10 D, E 72) A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the overall duration of this project if it is managed using critical chain methodology? ActivityPredecessor LengthAcivityPredecessor Length 16 20 20 10 D, E
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts