Question: A project manager at a projectized organizational is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20%

  1. A project manager at a projectized organizational is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date. Which of the following should the project manager do NEXT?
  • Ask the functional manager to release the 20% of allocation from the secondary project
  • Ask the sponsor to negotiate with the project manager from the secondary project
  • Ask the PMO to assign additional resources
  • Ask the project manager of the secondary project to release the resource
  1. Because of space limitations, there has been a long history of contention among team. Which of the following actions can the project manager take that would MOST contribute to project?
  • Ignore the issue
  • Require staff to focus on deliverables
  • Replace team members
  • Hold an open dialogue to build consensus
  1. A project manager is assigned a global team. The project manager is having difficulty understanding some of what is communicated during conference calls. Which of the following is the BEST to address this issue?
  • Reassign the project manager to a different project
  • Transfer the project team members who are difficult to understand to another project
  • Inform the sponsor and ask for feedback on how to address the issue
  • Communicate critical conversations and decision points via email
  1. A project manager is working on a project, and the team has determined the task information. Which of the following should be done NEXT?
  • Set a baseline
  • Grain steering approval
  • Determine the critical path
  • Link the predecessors

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!