Question: A project manager does not have much time to spend on planning before the mandatory start dates arrives. He therefore wants to move through planning

A project manager does not have much time to spend on planning before the mandatory start dates arrives. He therefore wants to move through planning as effectively as possible. What advice would you offer?

Select one:
a. Document all known the known risks before you document the high-level assumptions.
b. Make sure you have a signed project charter and then start the WBS.
c. Finalize the quality management plan before you determine quality metrics.
d. Create an activity list before creating a network diagram.