Question: I 0. A project manager doe~ not have much time to spend on pl.urning before the mandatory start date arrives I-le therefore wants to mow
I 0. A project manager doe~ not have much time to spend on pl.urning before the mandatory start date arrives I-le therefore wants to mow through planning as effectively as possible. \.\That advice would you offer?
A. Make su.re you have a signed project charter and then start the WBS.
B. Create an activity list before ..:reating a network diagr;un.
C. Document all the known risks before you document the high-level .1ssumptions.
D. Finalize the quality management plan before you determine quality metrics.