Question: A project manager for a large, ongoing film project is under a tight deadline to finish each of the projects three phases. The executives have

A project manager for a large, ongoing film project is under a tight deadline to finish each of the projects three phases. The executives have decided to increase the budget and time to ensure their standards are met. The project manager has updated the schedule to reflect the increases. What should the project manager do next?

  • A. Review the requirements in the quality management plan
  • B. communicate the updated schedule to the stakeholders
  • C. add the tasks mentioned to the schedule management plan
  • D. update the success criteria in the scope management plan