Question: A project manager for Durable Construction Co. is about to build a house involving the following six activities: ACTIVITY PESSIMISTICI Start A B IC DURATION

A project manager for Durable Construction Co. is about to build a house involving the following six activities: ACTIVITY PESSIMISTICI Start A B IC DURATION ESTIMATES (days) PRECEDES OPTIMISTICI MOST LIKELY A, B IC,D 44 50 D 45 601 E 42 45 31 40 27 36 End 581 70 561 75 481 49 39 82 D IF What is the estimated expected (mean) duration for project completion? Multiple Choice 160 days 170 days