Question: A project manager for Durable Construction Co. is about to build a house involving the following six activities: DURATION ESTIMATES (days) ACTIVITY PRECEDES OPTIMISTIC MOST

A project manager for Durable Construction Co. is

A project manager for Durable Construction Co. is about to build a house involving the following six activities: DURATION ESTIMATES (days) ACTIVITY PRECEDES OPTIMISTIC MOST LIKELY PESSIMISTIC Start A B AB C, D D E F F End 44 45 42 31 27 58 50 60 45 40 36 70 56 75 48 49 39 82 D E F What is the probability that the critical path for this project will be completed within 210 days? Select one: C a. 0.9987 O b. 0.5000 O C. 0.9544 O d. 0.8413