Question: The Project Manager is about to begin a project comprised of the following six activities: DURATION ESTIMATES (days) ACTIVITY PRECEDES OPTIMISTIC MOST LIKELY PESSIMISTIC Start
The Project Manager is about to begin a project comprised of the following six activities:
| DURATION ESTIMATES (days) | ||||
| ACTIVITY | PRECEDES | |||
| OPTIMISTIC | MOST LIKELY | PESSIMISTIC | ||
| Start | A, B, C | |||
| A | D | 38 | 50 | 62 |
| B | E | 90 | 99 | 108 |
| C | End | 85 | 100 | 115 |
| D | F | 19 | 25 | 31 |
| E | End | 91 | 100 | 115 |
| F | End | 62 | 65 | 68 |
What is the probability that this project will be completed within 205 days?
Select one:
A.
0.8413
B.
0.6826
C.
0.9772
D.
0.9544
E.
0.9987