Question: The Project Manager is about to begin a project comprised of the following six activities: DURATION ESTIMATES (days) ACTIVITY PRECEDES OPTIMISTIC MOST LIKELY PESSIMISTIC Start

The Project Manager is about to begin a project comprised of the following six activities:

DURATION ESTIMATES (days)
ACTIVITY PRECEDES
OPTIMISTIC MOST LIKELY PESSIMISTIC
Start A, B, C
A D 38 50 62
B E 90 99 108
C End 85 100 115
D F 19 25 31
E End 91 100 115
F End 62 65 68

What is the probability that this project will be completed within 205 days?

Select one:

A.

0.8413

B.

0.6826

C.

0.9772

D.

0.9544

E.

0.9987

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!