Question: A project manager is analyzing progress on a project to make a 1 0 - minute documentary. It s the end of week two on
A project manager is analyzing progress on a project to make a minute documentary. Its the end of week two on this three week project. The actual cost is $ They have minutes of usable film. The budgeted total cost is $ Determine PV EV CV CPI, SV and SPI.
a First, map each description to an EVA category. Then, fill in the table.