Question: Problem 1 Week AC PV EV CV CPI SV SPI 2 $ 7 2 , 0 0 0 A project manager is analyzing progress on
Problem
Week AC PV EV CV CPI SV SPI
$
A project manager is analyzing progress on a project to make a minute documentary. Its the end of week two on this three week project. The actual cost is $ They have minutes of usable film. The budgeted total cost is $ Determine PV EV CV CPI, SV and SPI.
a First, map each description to an EVA category. Then, fill in the table.
b What do the SPI and CPI values mean in this example? Explain in plain English.
c Could a project or task be where we expect in terms of cost but behind on schedule? Hint: see formulas