Question: A project manager is assigned to a project team midway through execution Several dependencies are impacting the project, and the project manager feeis the team
A project manager is assigned to a project team midway through execution Several dependencies are impacting the project, and the project manager feeis the team is not adequatel What should the project manager do first? Convene an impact analysis meeting Escalate the issue to the product owner Review the stakeholder register Consult the communications management plan