Question: A project manager is leading an effort to launch a new software throughout their company. At the end of week 3 , there are worries
A project manager is leading an effort to launch a new software throughout their company. At the end of week there are worries that the project is in trouble because activity C has not yet begun...and half of the total project budget has already been spent. Fortunately, activity A is done, and B is halfway complete.
Activity
Time
Predecessor
Cost
A
B
A
C
A
D
B C
What is the total expected cost of the project, or Budget at Completion BAC
$
At the end of week three, what is the Planned Value, or the cost of the work that is scheduled to be done?
$
At the end of week three, what is the Earned Value, or the budgeted cost of the work actually finished?
$
What is the actual amount spent, or Actual Cost, at the end of week
$
Based on these numbers, the project is:
Select
budget.
Select
schedule.
If the performance trend continues, the project will end up costing
$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock