Question: A project manager is leading an effort to launch a new software throughout their company. At the end of week 3 , there are worries
A project manager is leading an effort to launch a new software throughout their company. At the end of week there are worries that the project is in trouble because activity C has not yet begunand half of the total project budget has already been spent. Fortunately, activity A is done, and B is halfway complete.