Question: A project manager is using Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 2 Activity Normal or

  1. A project manager is using Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 2

Activity

Normal or Expected time t (week)

Normal cost (RM)

Crash time (weeks)

Crash cost (RM)

1-2

2

1,000

1

2,000

1-3

7

1,000

3

3,000

2-3

4

2,000

2

4,000

2-4

3

1,000

1

5,000

2-5

2

2,000

1

4,000

Draw a network diagram representing the project

Determine the least cost of reducing the project completion time by 3 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!