Question: A project manager is using Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 2 Activity Normal or
- A project manager is using Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 2
Activity | Normal or Expected time t (week) | Normal cost (RM) | Crash time (weeks) | Crash cost (RM) |
1-2 | 2 | 1,000 | 1 | 2,000 |
1-3 | 7 | 1,000 | 3 | 3,000 |
2-3 | 4 | 2,000 | 2 | 4,000 |
2-4 | 3 | 1,000 | 1 | 5,000 |
2-5 | 2 | 2,000 | 1 | 4,000 |
Draw a network diagram representing the project
Determine the least cost of reducing the project completion time by 3 weeks