Question: Questions: A project manager is using Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 1 table

Questions:
A project manager is using Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 1
\table[[Activity number,Activity name,Duration in hours,Predecessor],[1,Date/Location,1,-],[2,Hotel booking,25,1],[3,Arrival,15,1],[4,On-site offers,20,1],[5,On-site program,10,2,3,4],[6,\table[[Send info to],[participants]],1,5,6],[7,Approval,30,7],[8,Event start,5,1]]
a) Draw a network diagram (AOA) and (AON) representing the project
(6)
b) What is the critical path of AOA for this project and how long does it take?
(2)
c) What is the shortest time in which this project can be completed?
(2)
(Total :10 marks)A project manager is using Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 1 a) Draw a network diagram representing the project b) What is the critical path for this project and how long does it take? c) What is the shortest time in which this project can be completed? (Total: 10 marks)
 Questions: A project manager is using Project Network Diagram to perform

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!