Question: A project manager is using the Program Evaluation and Review Technique to make a project schedule. The expected project completion time for this project is

A project manager is using the Program Evaluation and Review Technique to make a project schedule. The expected project completion time for this project is 45 months with the project variance as 16.

a)

What is the probability that the project will be completed within 43 months?

69.15%

. 0%

30.85%

50%

None of the above

b) What is the expected due date that would yield a 9.85% chance of completion? (keep 2 decimals)