Question: A project manager meets with a resource manager and asks to move resources from project A to project B . What is the MOST likely

A project manager meets with a resource manager and asks to move resources from project A to project B. What is the MOST likely reason for this request?
A problem has caused delay beyond the project manager's ability to control.
An activity has taken longer than planned.
An activity was missed because a work breakdown structure was not created.
Project A has become higher priority within the organization.
 A project manager meets with a resource manager and asks to