Question: A project manager needs a systems administrator as a resource on a project. The project manager approaches the operations manager to obtain the resource. In
A project manager needs a systems administrator as a resource on a project. The project manager approaches the operations manager to obtain the resource. In Which of the following organizational structure is the project manager most likely operating?
A. Hybrid
B. Projectized
C. Functional
D. Matrix