Question: A project manager performs Earned Value Analysis and finds the following results ? :A project manager performs Earned Value Analysis and finds the following results

A project manager performs Earned Value Analysis and finds the following results ?
A project manager performs Earned Value Analysis
:A project manager performs Earned Value Analysis and finds the following results EV: 250,000; PV: 200,000; AC 275,000 BAC is 500,000 What is right EAC =450,000 BTC=550,000 BTC=450,000 EAC=550.000