Question: A project manager performs Earned Value Analysis and finds the following results: EV=250,000, PV=200,000. AC=275,000, BAC= 500,000. Which choice is correct? O A. EAC =


A project manager performs Earned Value Analysis and finds the following results: EV=250,000, PV=200,000. AC=275,000, BAC= 500,000. Which choice is correct? O A. EAC = 400,000 O B. EAC = 550,000 O C. BTC = 400,000 O D. ETC = 75,000