Question: A project manager received a high - priority change request from a key stakeholder. The project manager logged the change and ensured that the purpose

A project manager received a high-priority change request from a key stakeholder. The project manager logged the change and ensured that the purpose of the change was clearly documented. They clearly understood the reason for the change. What is the next step in the change process?
Document decision notes
Approve the change immediately
Provide implementation options
Evaluate the change