Question: A project manager sends out requests for regular status meetings and daily standup meetings during the project setup phase. However, business stakeholders are declining the

A project manager sends out requests for regular status meetings and daily standup meetings during the project setup phase. However, business stakeholders are declining the meetings.
What should the project manager do?
A.Check why meetings are declined
B.Re-share communications plan
C.Set up a project team ground rules
D.Hold a project kick-off meeting