Question: A project manager sends requests for regular status meetings and daily standup meetings during the project's setup phase. However, business stakeholders are declining the meetings.


A project manager sends requests for regular status meetings and daily standup meetings during the project's setup phase. However, business stakeholders are declining the meetings. What should the project manager do? O Hold a project kick-off meeting O Discuss optional stakeholder representation O Set up a project team room Create a communications management plan