Question: A project manager used a control chart to determine whether a process was stable or not, and to determine if its performance was predictable. He
A project manager used a control chart to determine whether a process was stable or not, and to determine if its performance was predictable. He determined the upper and lower specification limits based on the contractual requirements. A set of eighteen data points were taken. Of these, consecutive data points were above the mean. What can you say about such a process?
A A process is considered as out of control if five consecutive data points are above or below the mean. Hence the process is out of control.
B A process is considered out of control if six consecutive data points are above or below the mean. Hence the process is within control.
C A process is considered as being within control if less than half the data points are above or below the mean. Hence the process is within control.
D A process is considered as out of control if seven consecutive data points are above or below the mean. Hence the process is out of control
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock