Question: A project manager writes weekly progress reports and adjusts the project timeline as the team completes tasks. At what stage of the project do these

A project manager writes weekly progress reports and adjusts the project timeline as the team completes tasks. At what stage of the project do these events occur?
Execution
Planning
Closing
Initiation