Question: A project network diagram has only 3 paths going from the start node to the end note. Their lengths are 18, 11, and 4, respectively.

A project network diagram has only 3 paths going
A project network diagram has only 3 paths going from the start node to the end note. Their lengths are 18, 11, and 4, respectively. What is the project duration (i.e., earliest possible project completion time)? Enter a whole number