Question: A project network diagram has only 3 paths going from the start node to the end note. Their lengths are 5, 23, and 4, respectively.

A project network diagram has only 3 paths going

A project network diagram has only 3 paths going from the start node to the end note. Their lengths are 5, 23, and 4, respectively. What is the project duration (i.e., earliest possible project completion time)? Enter a whole number

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!