Question: A project network has the following paths. How much slack does path ABEGHI have? Path Duration ABDFHI 4 1 ABEFHI 4 8 ABEGHI 5 5

A project network has the following paths. How much slack does path ABEGHI have?
Path Duration
ABDFHI 41
ABEFHI 48
ABEGHI 55
ACGHI 40
A project network has the following paths. How much slack does path ABEGHI have?
Path Duration
ABDFHI 41
ABEFHI 48
ABEGHI 55
ACGHI 40
14
7
0
55