Question: A project network is shown below. Pessimisti Precedence Activities Activity A B D E F G H I AB D. E E E, F Optimistic

A project network is shown below. Pessimisti

A project network is shown below. Pessimisti Precedence Activities Activity A B D E F G H I AB D. E E E, F Optimistic Most Probable Time (weeks) 1 5 2 4 4 8 2 4 10 12 4. 10 1 3 1 2 2 5 10 8 12 8 14 16 5 3 7 What is the probability that the project can be completed within 27weeks? A. Approximately 0.8980 or 89.8% O B. Approximately 0.102 or 10.2% C. Approximately 0.5 or 50% D. Approximately 0.7704 or 77.04%