Question: draw an activity-on node network diagram for the following project, including the estimated time for each activity. b) what is the critical path, expected duration

draw an activity-on node network diagram for the following project, including the estimated time for each activity.

draw an activity-on node network diagram for theb) what is the critical path, expected duration and variance of the project?

c) using the expected times you calculated, which activities have slack and how much?

Activity A B D E F H Optimistic Time(weeks) Time (weeks) Time (weeks) 2 3 4 5 12 4 6 8 11 3 7 1 9 4 2 Most likely Pessimistic Predecessor A, B 1 7 9 2 11 8 6 4 14 3 13 12 16 10 C C F C G, H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!