Question: draw an activity-on node network diagram for the following project, including the estimated time for each activity. d) what are the chances that you can
draw an activity-on node network diagram for the following project, including the estimated time for each activity.

d) what are the chances that you can finish this project in 34 days?
e) if I gave you an extra resources (say 5 person-weeks of work) what would you do with them?
Activity A B D E F H Optimistic Time(weeks) Time (weeks) Time (weeks) 2 3 4 5 12 4 6 8 11 3 7 1 9 4 2 Most likely Pessimistic Predecessor A, B 1 7 9 2 11 8 6 4 14 3 13 12 16 10 C C F C G, H I Activity A B D E F H Optimistic Time(weeks) Time (weeks) Time (weeks) 2 3 4 5 12 4 6 8 11 3 7 1 9 4 2 Most likely Pessimistic Predecessor A, B 1 7 9 2 11 8 6 4 14 3 13 12 16 10 C C F C G, HStep by Step Solution