Question: A project task has an early start time of 4, a late start time of 9, an early finish time of 7, and a late
A project task has an early start time of 4, a late start time of 9, an early finish time of 7, and a late finish time of 12. What is the tasks slack?
| A. | 9 | |
| B. | 6 | |
| C. | 5 | |
| D. | 4 | |
| E. | 0 | |
| F. | 7 |