Question: A project team identifies risks based on the information from previous similar projects The above statement best explains which of the following risk identification techniques?Group
"A project team identifies risks based on the information from previous similar projects" The above statement best explains which of the following risk identification techniques?Group of answer choicesProcess flowchartsRisk registerWBS analysisAnalogy
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer