Question: A project team identifies risks based on the information from previous similar projects The above statement best explains which of the following risk identification techniques?
"A project team identifies risks based on the information from previous similar projects"
The above statement best explains which of the following risk identification techniques?
Group of answer choices
WBS analysis
Risk register
Process flowcharts
Analogy
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
