Question: A project team is considering using a newly developed material on its project. There would be a considerable cost savings achieved by using this material,

A project team is considering using a newly developed material on its project. There would be a considerable cost savings achieved by using this material, but the quality of the material is unknown. To prevent possible rework in the future, the project team chooses not to use this material. What risk response strategy is being used?




Step by Step Solution

3.46 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The risk response strategy being used by the project team is Avoidance In risk management a... View full answer