Question: A project to develop a county park has an actual cost in month 1 7 of N$ 3 5 0 , 0 0 0 ,

A project to develop a county park has an actual cost in month 17 of N$350,000, a planned cost of N$475,000, and a value completed of N$300,000. Find the cost and schedule variances and the three indexes. (N$000) Comment on the current state of the project. Month AC PV EV
17 N$350 N$475 N$300
CV
CPI
SV
SPI
CSI