Question: A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed

A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes. (three indices = CPI, SPI, and CSI) o Complete calculations for the project as a whole (DO not do it for individual activities)