Question: A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed

A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes.

Step by Step Solution

3.25 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

000 Month AC PV EV 17 350 475 300 ... View full answer