Question: A project was running behind schedule because of the programming tasks which areWhich of the following accurately represents and is TRUE about the SDLC? on

A project was running behind schedule because of the programming tasks which areWhich of the following accurately represents and is TRUE about the SDLC? on the critical path. In order to deal with the problem, the project manager hired additional human resources so that the duration would be shortened. Which of the following did the project manager do? Group of answer choices Crash the project Fast track the project Baseline the project Gate the project