Question: A project whose critical path has an estimated time of 740 days with a variance of 256 has a 73% chance that the project will

A project whose critical path has an estimated
A project whose critical path has an estimated time of 740 days with a variance of 256 has a 73% chance that the project will be completed before which day (rounded to nearest day)? 0 590 833 0 650 O 750 864