Question: Question 14 5 pts A project whose critical path has an estimated time of 950 days with a variance of 256 has a 73% chance

Question 14 5 pts A project whose critical path
Question 14 5 pts A project whose critical path
Question 14 5 pts A project whose critical path
Question 14 5 pts A project whose critical path has an estimated time of 950 days with a variance of 256 has a 73% chance that the project will be completed before which day (rounded to nearest day)? 590 645 830 730 0 960 Question 16 5 pts Suppose that the last four months of sales were 8, 10, 15 and 12 units, respectively. Suppose further that the last four forecasts were 10, 9, 11, and 6 units, respectively. What is the Mean Absolute Percent Error (MAPE) of these forecasts? O 0.2791 O 0.3604 0.5437 0.1854 0.4104 Question 17 5 pts What is the forecast for May using a four month weighted moving averago (weights: last month - 25000, two months ago 15000, 3 months ago - 40000, 4 months ago - 20000)? Nov. Dec. 39 36 Jan Feb Mar 38 42 48 April 46 43.1 463 459 O 415 O 443

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!