Question: project whose critical path has an estimated time of 950 days with a variance of 256 has a 73% chance that the oject will be

project whose critical path has an estimated time
project whose critical path has an estimated time of 950 days with a variance of 256 has a 73% chance that the oject will be completed before which day (rounded to nearest day)? 730 590 645 980 830