Question: A project with nine activities is shown below. We also have the following information: Activity =A, duration =23 days Activity =B, duration =32 days Activity
A project with nine activities is shown below. We also have the following information: Activity =A, duration =23 days Activity =B, duration =32 days Activity =C, duration =15 days Activity =D, duration =19 days Activity =E, duration =32 days Activity =F, duration =22 days Activity =G, duration =6 days Activity =H, duration =22 days Activity =K, duration =47 days The expected project completion time is days