Question: We also have the following information: Activity = A , duration = 2 6 days Activity = B , duration = 3 0 days Activity

We also have the following information:
Activity =A, duration =26 days
Activity =B, duration =30 days
Activity =C, duration =26 days
Activity =D, duration =8 days
Activity =E, duration =14 days
Activity =F, duration =17 days
Activity =G, duration =24 days
Activity =H, duration =24 days
Activity =K, duration =9 days
Assuming the latest finish time of the project equals the earliest finish time of the project, the latest finish time of activity B is at the end of day