Question: We also have the following information: Activity = A , duration = 3 2 days Activity = B , duration = 1 4 days Activity

We also have the following information:
Activity =A, duration =32 days
Activity =B, duration =14 days
Activity =C, duration =21 days
Activity =D, duration =27 days
Activity =E, duration =34 days
Activity =F, duration =26 days
Activity =G, duration =24 days
Activity =H, duration =12 days
Activity =K, duration =20 days
Assuming the latest finish time of the project equals the earliest finish time of the project, the latest finish time of activity F is at the end of day
 We also have the following information: Activity =A, duration =32 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!